Pod Insights Catalyst with Shayle Kann The Green Blueprint: Terrawatt Infrastructure’s billion-dollar strategy About this episode Editor's note: With the Trump administration's efforts to roll back California's electric trucking rules, there's new attention on heavy duty transport right now. So we're bringing you a deep dive into the industry, an episode of The Green Blueprint on Terawatt Infrastructure's $1 billion strategy to build charging depots.
In 2021, Neha Palmer co-founced Terrawatt Infrastructure with a bold mission: create the backbone for America's electric trucking revolution.
Within its first year, Terrawatt secured a billion-dollar investment. But as the company developed plans for a nationwide charging network, it confronted the daunting challenge of building infrastructure for an electric truck market that barely existed.
High-profile bankruptcies like Nikola Motors cast long shadows over the sector's viability, raising questions about whether heavy-duty transport can truly be electrified.
In this episode, Lara talks with Neha about how Terrawatt aims to transform freight transport despite market skepticism. Neha explains Terawatt’s strategic approach to site selection, innovative charging designs for fully-loaded trucks, and the vision for a revolutionary California-to-Texas network.
Credits: Hosted by Lara Pierpoint. Produced by Erin Hardick. Edited by Anne Bailey and Stephen Lacey. Original music and engineering by Sean Marquand. Stephen Lacey is our executive editor.
Transcript 0:00 Speaker 00 Hi, everyone. It's Daniel Waldorf. I'm the producer for Catalyst. There are new headwinds in electric trucking right now. This month, the Trump administration sued the state of California over its efforts to electrify heavy-duty transport. That is on top of the administration's cuts to funding for charging infrastructure, plus the tariffs that slow down the trucking businesses that depend on the ports. So we're bringing you a deep dive into electrified trucking. It's an episode of The Green Blueprint, another Latitude show that goes behind the scenes with climate tech companies, exploring the stories of building first-of-a-kind projects. This one is about Terawatt Infrastructure, which builds heavy-duty charging infrastructure. Host Laura Pierpoint brings CEO Neha Palmer onto the show to talk about how
0:43 Speaker 00 Terawatt secured a $1 billion investment and built a charging depot near the ports of Los Angeles and Long Beach. This was at a time when Nikola Motors bankruptcy really brought a lot of skepticism to the heavy-duty electrification space. We'll be back next week with a new Catalyst episode, but for now, here's Laura and Neha.
1:03 Speaker 01 Latitude Media, podcast at the frontier of climate technology.
1:09 Speaker 02 The trucking industry has an emissions problem. Heavy-duty trucks make up less than 5% of vehicles on the road, but they generate nearly 25% of transportation emissions. Electrifying these massive vehicles seems like a no-brainer, but some skeptics say it's just not possible. Neha Palmer, however, is not one of those skeptics.
1:32 Speaker 03 This is a transition that is happening.
1:35 Speaker 02 When Neha Palmer co-founded Terawatt Infrastructure in 2021, she wasn't just building a charging company. She was creating an entirely new category of infrastructure. While passenger EVs had a decade-long head start, heavy-duty electric trucks were still in their infancy. But she saw their path to electrification as inevitable.
1:57 Speaker 03 The analogy I love to use is transition that happens once every century. So you had the railroads, and that required a significant amount of investment very quickly. Then you had the National Highway Network, and now you have an overlay On both of those, really, which is electrification of those modes of transport.
2:14 Speaker 02 The complexity of the challenge is staggering. A single site for heavy-duty truck charging requires finding the perfect location, securing megawatts of power, navigating the permitting processes that have never seen this type of infrastructure before, and then convincing fleet operators to take a chance on a technology that's still evolving. And the road has been bumpy.
2:36 Speaker 04 Well, this is a trouble sign for the electric vehicle industry as Nikola Motors headquartered in Coolidge filed for bankruptcy this morning.
2:45 Speaker 02 Earlier this year, Nikola Motors, once a promising pioneer in zero-emission trucks, filed for bankruptcy after a spectacular rise and fall. Critics pointed to it as proof that electrifying heavy-duty transport was simply too difficult.
3:00 Speaker 03 You know, I certainly hope it's a blip. You know, we need as much investment into the technology or the vehicle itself as we do in the charging to make all of this a reality.
3:18 Speaker 02 But in April, Terawatt proved the doubters wrong when it opened its first commercial heavy-duty charging depot near the ports of Los Angeles and Long Beach. The ports are technically separate but operate as one big complex. They're the biggest container ports in the US. And it wasn't just a charging station. It was the first node in what will become a network of sites across all of Southern California.
3:40 Speaker 03 In California, we have built what I think is the best network of sites, and three of them will be live this year, with the Port of LA Long Beach site being the first one. We'll have a third one that's further north, near the intermodals. And so with those three sites, we kind of have amazing coverage of the entire LA basin.
3:59 Speaker 02 I'm Laura Pierpoint, and this is The Green Blueprint, a show about the architects of the clean energy economy. We've already invented most of the solutions needed to decarbonize the global economy. But many of these technologies are not yet commercial, and they need to get financed and built at scale. We don't have decades to get them commercialized. We have years. This week, we're talking about the monumental challenge of electrifying heavy-duty trucking with Neha Palmer, co-founder and CEO of Terawatt Infrastructure.
4:32 Speaker 03 We know that this is a trillion-dollar investment over years. And so the scale that we're talking about and the impact that we need to make, even with a few sites, is going to require lots of capital.
4:49 Speaker 05 Demand flexibility is now an essential part of the data center's speed-to-power playbook. But how do data centers actually curtail load? GridBeyond is the end-to-end solution for flexible energy management. GridBeyond's advanced derms and VPP platform is tailored to what data centers care about most: maximizing reliability, intelligently meeting curtailment obligations, reducing costs, and managing all your distributed resources in one place. Ready to transform your distributed energy management? Get started at gridbeyond.com. Catalyst is brought to you by Antenna Group, the communications and marketing partner behind the most influential companies in energy, climate, and infrastructure. For three decades, Antenna has helped ambitious companies stand out, build market leadership, and become category-defining
5:34 Speaker 05 brands. From breakthrough startups to global industry leaders, their team brings the expertise, relationships, and track record to accelerate your momentum. Learn more at antennagroup.com.
5:47 Speaker 06 The power plant for the modern grid isn't a building. It's a network. Energy Hub's derms platform connects batteries, EVs, thermostats, and commercial and industrial sites into virtual power plants that over 230 utilities dispatch as reliable grid capacity day in, day out. VPPs deploy in 60 to 100 days at 40% to 60% less cost than traditional infrastructure, and they perform like conventional generation from day one. Learn about the flexibility platform for the modern grid at energyhub.com.
6:23 Speaker 02 Terawatt's approach is ambitious. Shortly after launching in 2021, the company secured a huge chunk of capital from investors. Very amazingly, you secured $1 billion in funding led by Vision Ridge just after you launched, really, this was about a year after you launched as a company. So can you tell us a bit about what convinced investors at that stage to make such a big commitment to your vision?
6:46 Speaker 03 When you think about our sites that we're starting to build out, the billion dollars is not going to last that long to build that many assets. And so it was really the vision from the beginning that this is not just a small-scale effort, it's going to be something that requires significant capital. And there'll have to be multiple billion-dollar raises, frankly, to get this even off the ground.
7:11 Speaker 02 Terawatt doesn't just install chargers. It acquires the real estate, works with utilities to secure power, installs chargers and associated infrastructure, and ultimately handles ongoing operations and maintenance.
7:24 Speaker 03 Really, our business model is investing into these sites and taking that CapEx burden away from our customers, allowing them to engage on a more OpEx basis, and also taking away the pain of working with utilities when they're used to buying fuel, of the time that it takes to put the construction together, all of the investment, and really making that a seamless process for them as they change to electric vehicles over time.
7:48 Speaker 02 Terawatt began piloting its business model in 2022. Then, in October 2024, it opened its first full-scale commercial site near LAX. This site is for passenger vehicles, and in this case, that mostly includes rideshare companies. It's not suited for big semi trucks.
8:05 Speaker 03 On the rideshare side, in dense urban markets where there's a lot of traffic, we're hearing from operators, it's cost-accretive for them to run EVs instead of traditional vehicles because of the fuel savings.
8:16 Speaker 02 The market momentum is slower for medium and heavy-duty charging. In part, that's because of what we mentioned at the top. The electric semi truck industry has struggled to take off. And it's tough to make the case for building chargers when there aren't trucks to charge. But Naya is optimistic that that market is going to tip with more big trucks being electrified.
8:43 Speaker 03 We've had almost close to 20 years of learning on the passenger side. On the electric truck side, it's certainly earlier days. And so you see a lot of the same things you saw on the passenger side. You're seeing improvements in battery pack costs and performance of the vehicles themselves. And as that starts to mature, you're starting to see more and more demand.
9:03 Speaker 02 The heavy-duty charging facility near the ports of LA and Long Beach that Terawatt opened this year is called Ranchero Dominguez. It features pull-through stalls that can accommodate full tractor trailers, which is a unique feature, and up to 125 trucks can charge there in one day. It marks the beginning of what Terawatt envisions as a network of charging stations all along the I-10 corridor, all the way from California to Texas.
9:29 Speaker 03 We call it kind of a corridor, but it would start in the port of Long Beach and go all the way to El Paso, Texas. And so allowing somebody in an EV truck to travel that confidently, knowing that they had charging along the way, that would accommodate the range of the vehicle.
9:45 Speaker 02 I talked with Neha about Terawatt's audacious plans for heavy-duty electric vehicles and her outlook for the industry. I started by asking her about the passenger vehicle side of the business because the LAX project was Terawatt's first full-build charging site and a major proof point for the company. So you started off near LAX. Can you talk a little bit, first of all, about why you chose that particular site?
10:07 Speaker 03 Yeah, so ride-share autonomous vehicles has always been a focus for us from the beginning, and a huge number of ride-share rides are initiated from airports. It's also a location that's near a major stadium and a lot of other good venues that would require ride-share to be part of that ecosystem. So the location just made sense from density of demand. It also was a site that was for sale. Oftentimes, we might be excited about a specific geography or geofenced area, but there may not be any flat lots or open lots or undeveloped lots to go and work with. So this was something that allowed us.
10:49 Speaker 03 To engage in this area and it was the right size for the application we were trying to put in, which was what ended up being about 30 chargers focused on passenger vehicles with enough space for, you know, driver's lounge and, you know, all the space for all of the electrical equipment, chargers, everything else that we needed. So the last piece that is always so important and it, I'm making it sound like an afterthought, but it really is the most critical thing and the thing that we almost always think about first once we identify a location is it had power. So it had five megawatts of power that was available from day one. We just had to start construction on our site and the utility had to do a little bit of construction on their end, but we knew that we could get
11:32 Speaker 03 that power from day one to allow us to serve that many chargers all at one time. So really it had that confluence. I call it the Venn diagram of the things we need, which are our customer demand, available real estate. It didn't have the right zoning at the time, but we worked on that. And then the last piece and the most important piece being the power available at the site as well.
11:53 Speaker 02 Okay. Well, let's talk a little bit about the development for the site. Can you walk us through some of the things that you had to do around permitting, site preparation, all that sort of stuff? What did it look like to get ready to build it?
12:02 Speaker 03 Yeah. And so this is something that's always fun when you're starting a new industry. I came from data centers and we had this whole pattern of recognition for data centers too. When it was early days, we'd go into new jurisdictions and people would say, I don't even know what that is. Certainly that everyone knows what that is in the world now, but for EV charging, there's oftentimes not any code available, the planning code for how do you permit, how do you entitle a EV charging hub? So we worked very closely with the city of Inglewood, who was a fan, who is a fantastic host for us here in this site to understand what their existing code was and how we might fit into it. It had to go through a whole process with the city council, the planning council to have them
12:47 Speaker 03 understand what the project was, what kind of benefits it would bring to the community. And then they had to actually put new language in their code to allow the entitlement of this. And so that's something that we find and. Many new, you know, AHJs or authorities having jurisdiction that we enter. They may have never seen this before, so we have the benefit of having done it now. We could hold up this template, but this was the first time. And so we did have to work through that process with the city. Again, they were, you know, super, super collaborative. And so we were able to do that, but that did take time. So it wasn't like, you know, day one, we have closed on this real estate site. We know exactly where to go to file for the permit, et cetera. There was a little bit of legwork to do ahead of that in the entitlements to get the right zoning for the site.
13:32 Speaker 03 And then there was a whole permitting process and kind of a little bit same thing again. There have not been many of these installations at this scale built anywhere. And so it takes some time to work with, you know, the city engineers to get them to understand like, here's what this looks like. Here is our electrical design. This is what a typical site looks like. And so we ran that process with the city again, again, very collaborative. But, you know, anytime you have to do a little bit of educating and collaborating, it does take more time.
14:02 Speaker 02 Sure. Okay. Well, and then let's talk for a second about your hardware supply. So there are a lot of different charging companies that supply hardware for passenger vehicle charging. So how did you think about that? How did you select your hardware provider? And is it kind of a single provider that you always work with? Or how do you think about your, your supply chain here?
14:19 Speaker 03 Yeah. So it's interesting you say supply chain because there's so many components, not just the chargers. For this site, for the chargers, you know, we wanted to make sure that we had a partner that was going to be working with us to maintain that high uptime. And so we worked with that partner really closely to make sure that, you know, any kind of visibility software we were building was going to be very compatible with their chargers. That's a level of integration that's generally not there. Generally, there is probably, you know, call it four to eight would be a large, large installation of chargers in one location. This is a much larger deployment that I think most charger companies are used to doing in one location. So the concept was a little bit different for them as well, I believe.
15:04 Speaker 03 And so working really closely with them to make sure that our software worked with their hardware. That we were able to do what we needed to do to have the remote network operating center, have the visibility they needed. So there was a lot of work upfront to make sure, and again, we're also deploying our software for the first time. So a lot of work to make sure that there was a level of collaboration. So when we look for hardware providers, obviously, the hardware has to work, it has to be high quality. But the real table stakes for us is collaboration. And so ensuring that they were willing and able to do that level of collaboration. Another piece is spare parts. It seems really simple that if you create chargers, you would have a full spare parts program, but that's not the case for all charger providers.
15:47 Speaker 03 So making sure that they had a robust program. Here in the US, oftentimes you have chargers coming from other geographies, and so they might be deeper there, but not here in the US. So deep spare parts program. And then also just techs that are available and understand that technology. Again, it's a very global supply base, and so you might have depth in Europe, but you may not have many techs that know that equipment here in the US. So really thinking through that whole aspect of how do we make sure that we're going to have the highest uptime we possibly can.
16:20 Speaker 02 And so kind of one last question about this, well, a couple of questions actually about this, about this commercial site. So one of the things that comes up pretty frequently on the show is the question around, do I use an engineering procurement or in construction firm to build something, or do I do it myself? And some really interesting impacts flow from those decisions, particularly when you're building things that are effectively first of a kind. So can you talk a little bit about how you were thinking about managing the construction on this first site? And what you ultimately decided?
16:50 Speaker 03 So for this first site, we did work with an EPC firm. And I think we learned a lot about working with an EPC firm. One thing that we learned is, you know, the civil aspect of our sites is very heavy. If you look at a site, it actually, I think sometimes people look and they're like, oh, that's interesting. It's like, you know, 30 chargers are nice and pretty, standing on the ground. But you don't see what's happening below ground, which is massive duct banks. We oftentimes put in extra capacity. So when the charger power might go up, we would have the Ability to actually make that change over pretty quickly. So future-proofing, underground, and so there's a lot of stuff happening below the grade. And I think that's one thing that we learned and that EPC, if you think about it, the civil trade,
17:33 Speaker 03 and I'm actually a civil engineer, is very local. So having that local expertise is very, very critical for the types of things we build because, you know, the type of soil that you're dealing with, the codes that are, you know, related to how much rainfall, you know, ends up in an area, et cetera, is oftentimes really contingent upon local expertise to understand those characteristics and how the local, you know, planning commissions and engineering leaders in those planning commissions will think about our construction. So something that we had to kind of learn the first time. And so how we contract in the future would be really taking that lesson in hand.
18:12 Speaker 02 With the first commercial site built, Neha and the Terawatt team turned their attention to their flagship heavy-duty project, Rancho Domingos at the Port of Long Beach, which had actually already been underway for years. More about that after the break.
18:32 Speaker 05 For data centers, connecting to the grid quickly means two things: building distributed energy and having a plan for demand flexibility. GridBeyond helps with both. GridBeyond's terms and VPP platform unlocks the potential of distributed assets and dispatches flexibility into the right market at the right time. And this is more than software. GridBeyond supports developers every step of the way, from modeling your highest ROI energy mix to orchestrating the full set of assets around a data center. The track record speaks for itself. GridBeyond manages over 1,400 sites and more than 3.7 gigawatts of load across Europe, the UK, and the US. Learn more at gridbeyond.com or click the link in the show notes.
19:14 Speaker 05 If you work in energy or climate, you already know the company's antenna group has helped build. For three decades, they've been the communications and marketing partner behind the industry's breakout companies, category creators, and market leaders. Today, their team is working across the Most consequential areas of the energy economy, from data centers and grid modernization to nuclear, geothermal, storage, critical materials, and next generation technologies. Antenna helps ambitious companies become the names everyone in the market knows, trusts, and wants to work with. They build reputation, elevate executives, drive demand, and turn momentum into market leadership. If your company is ready to lead its market, Antenna is ready to help you get there. Visit antenna group.com.
19:58 Speaker 06 When you harness the power of millions of DERs in a VPP and put artificial intelligence behind the dispatch, the outcomes exceed conventional generation. Energy Hub's DERMs platform has been trained on years of real dispatch data from over 2.6 million DERs, so utilities can plan with confidence. That means consistent load reduction across a four-hour event window, even during the widest, most uncertain peak periods. Utilities target, shape, and verify capacity down to the meter. Unlock flexible capacity that costs 40% to 60% less to deploy than traditional infrastructure in a fraction of the time it takes you to break ground on a peaker plant. Learn more at energyhub.com.
20:44 Speaker 02 Okay, this is very cool. And it sounds like tons and tons of lessons learned from this first site that then launched you into building your second site at the Port of Long Beach. So can you talk a little bit about how that project got started? At which point you started thinking about, you know, doing this particular project, working into the heavy-duty vehicle space? How did that all begin?
21:03 Speaker 03 So it's interesting, you know, our vision for the company really from the very beginning was focused on being able to electrify the heavy freight industry. And so the gleam in our eye was this segment. You know, we started engaging in the search for sites right when we started this business, you know, in early 21. Heavy-duty fleets tend to focus on locations that are near ports, in warehouse hubs, near intermodals. And so the Port of L.A. Long Beach was a location where there already is an intense push for electrification. There is a green lane at the port. So if you are in a zero-emission vehicle, You actually can get into the port faster with less wait time. Time is money for these guys. And so there's some significant upside for them to be able to do that.
21:47 Speaker 03 In Southern California, you also have something called the Ware Rules, where non-zero emission vehicles going in and out of warehouse hubs can start to incur fines for those warehouses. And so there is a push in the area for electrification with the port kind of being ground zero, the nexus of a lot of those efforts. And so finding a site near the port was kind of our first order of business when we started the company. And so it took us a while to find an ideal site. And when we did, it was pretty expensive. You know, it was probably going to be the biggest single real estate investment we had in the portfolio at the time. As a result, you know, we had to look really carefully at this investment and make sure it was the right location. Again, close to the port, but not in the port or on top of the port.
22:30 Speaker 03 So really understanding the characteristics of the flow of traffic from the port to different locations that those vehicles go to. Understanding the density of the flow of traffic because, you know, the Porto Valley Long Beach is the biggest container port here in the US. Freight goes in every single direction from that port. Are we on the right trajectory coming out of that site? So we did a lot of interesting things, everything from, you know, looking at anything that was available publicly from the Department of Transportation on freight flows, all the way to having someone just stand on the corner one day and count how many trucks went by in a specific two-hour period. So we really put a lot of thought and energy into deciding on this as a location
23:14 Speaker 03 for that really important first heavy-duty site.
23:18 Speaker 02 I love that story so much because I feel like so often we tell the stories of guts and glory for startups. And then it's really important to remember that some of what makes startups successful is exactly that, is an employee with a lawn chair sitting on the side of the freeway counting trucks at various points to influence how this decision went. And can you say a little bit about how that felt to kind of finally make a decision on this site? Because this was a pretty huge moment for the company to ultimately make this down selection and put, as you put it, like a fair amount of money on the line to make this site acquisition. Happen.
23:50 Speaker 03 I mean, the location has to be there. And that's why I talked about the Venn diagram. So we got comfortable with the location. This site also had something really incredible where you don't find this in many locations, which is seven megawatts of power available from day one. So that amount of power allowed us to do a lot of great things with the site. It was, you know, a corner lot. It had the right dimensions. It had a lot of space. So the site characteristics were great as well. You know, we had started to build these other sites. And so we kind of had an idea of what that process is for entitlements. So kind of everything started to tick all the boxes and that got us comfortable with it.
24:30 Speaker 03 But ultimately, we got super excited, actually, not just comfortable, excited about this location. Based on everything I just said, and we're excited to get this into our portfolio and under construction.
24:43 Speaker 02 So and then you're starting to design the site. So let's talk a little bit about this. One of the things that you had mentioned earlier was that you offer the opportunity for folks to pull in, not just with these bobtail sort of front end of the trucks, but really a fully loaded truck that actually has a trailer behind it. So were you already sure at that point that you wanted to offer that kind of charging capability? Or were you really thinking about, you know, what would the site layout look like? What were some of the trade offs around these different options for charging?
25:09 Speaker 03 So again, there's very few sites that have this scale of power and size that would allow that many chargers in one location and that many trucks to charge in one location. So we were kind of, you know, I wouldn't say, you know, making it up, but we were doing a lot of kind of product assessment and design to understand what would customers need. And if you look at a lot of the sites that are out there today, and even sites that customers have behind their fence, when they have the charging, it's usually just for a bobtail stall. So this was a little bit of a tug of war between the finance team and the product team. The product team came from places that had worked with semi trucks before. And so they really were pushing for those pull through stalls, saying, hey, if you look at the traffic flow patterns,
25:51 Speaker 03 they're going into the port or out of the port with the trailer attached to their tractor. It's going to be a really big lift for them to have to find a. Place to put the track, you know, the trailer, detach it, come in and charge, or you know, just be in a position where they don't have the trailer for whatever reason, they're between loads, to come back to the site, charge, and then go back and get their trailer, just a lot of work. And so, wouldn't be really a great customer experience if they had to do that. The tussle with the finance team was, well, if you have more chargers, you can potentially make more revenue from a site, right? And have more utilization. So, we landed kind of on a compromise, but we wanted to optimize the site for the pull-throughs. So, we got as many pull-throughs on the site as possible.
26:35 Speaker 03 And then when we had more power and space left, we added in some bobtail charging that will also allow, you know, smaller box trucks or even light-duty vehicles that need a huge amount of power, a high-power charge, to charge there. And when we had, you know, the kickoff event, we had a bunch of customers in the site, and they were all just marveling and really kind of gleeful about the fact that we had that many pull-through stalls.
26:59 Speaker 02 That's awesome. I can't wait to ask you a year from now how the utilization goes on both sides of those. I'm sure you all are dying to know that, too. Very cool. Let's talk about those customers for a sec because they're obviously very key to the equation here. So, can you say a bit about what your customer interactions were like, particularly for this project? When did you start engaging them to understand what they might want and what sort of contracts they might be willing to sign up for and when? And how did those, how did those negotiations go?
27:24 Speaker 03 Yeah, so we started engaging customers the minute we had the site. It is really hard to have a conversation with a customer if they can't even imagine the location. So, generally speaking, we don't start conversations until we have the specific site in mind, and even a layout. That said, what's interesting is it takes us, call it 18 months to 24 months, to find a site, get it entitled, permitted, constructed, and then an operational. Most vehicles make vehicle purchasing decisions at the most a year in advance, sometimes six months in advance. So, they may decide that they want to buy a few EVs and, you know, have those six months later. Charging doesn't come that quick. So, for this first one, it was a little bit of lining up those timelines. And so, one thing that we did see is we got close-
28:09 Speaker 03 Or and closer to project completion, a lot more engagement from these fleets. Because they could actually come to the site and see, oh, you've got this thing paved. And this is what the flow looks like and it's really going to come to fruition. I think there is in any industry that's new and nascent, a lot of discussion of we could build this or we could build that by, but by having actually done it and it's in site and operational. We actually saw even the week before we launched, you know, we were doing site tours with lots of customers. And that turnaround from site toward a contract was starting to happen a lot faster. Because of course it's ready to go from day one, but also just being able to see it is everything.
28:48 Speaker 02 Very cool. So can you say a bit more in detail? When was the first customer contract signed? Like what had you done or completed at the site that got the first person in the door to say yes? And actually sign on the dotted line?
28:59 Speaker 03 It honestly was about two years ago. So it was a customer that has pretty good experience with electric vehicles. They're one of the first movers in the industry. They have a larger fleet of EVs than most fleets do. I think they have well over 50 right now. And so they had some good experience where, and they were at a point where they were starting to outgrow their onsite charging. And they're also located close to us. So again, it was a good validation of that location selection. But the conversation really was like, hey, we've never done this offsite. We don't know how it's going to work. We'll take a chance with you guys. You know, there was some pre-existing relationships there that maybe helped grease the skids.
29:41 Speaker 03 But you know, they really were taking a chance that we were going to do what we said, build the site, deliver it. And then it would fit into their operations. And so now that it's live, I'm super excited to see how it fits in. I think it's going to be a lot more utility than they probably thought. This does open up a lot of different use cases like top off charges. The amount of power we have per charger allows it to charge, you know, a vehicle to charge much faster than most behind the fence chargers. And so having that capability can sometimes allow for a double shift of a vehicle. Where if it was a slower charge, they could use it for one run, has to come back to the yard, spend, you know, six to 12 hours charging and then can go out again. But if you can, you know, top off, you might be able to get two runs in a day.
30:24 Speaker 03 And all of a sudden that utilization of that vehicle is doubled. So, you know, I think those are the types of conversations we were having, the hopes that they had that we had. And now we'll see how this actually plays out.
30:35 Speaker 02 So my next question is how? As you're building this site at the port, you're obviously, I'm sure, in the process of thinking about your next site and the one after that and the one after that and a whole fleet of sites to come, particularly on the I-10 corridor in California, but maybe elsewhere too. So tell us about what comes next. What is the next site that's going to come online? How are you thinking about your future build out? How many sites are you working on all at once?
31:01 Speaker 03 Yeah, so for this, this definitely is the first of a couple of projects. We have our next site that will come online in the summertime. That will be in the inland empire, which is after a vehicle goes to the port, it generally goes to the inland empire, which is the giant warehouse district for the port here in California. And so we'll have a second site there in a few months. And it really is thinking about this as a network, right? These are moving assets. I mentioned that top off charge that could be really beneficial to higher utilization of these pretty expensive vehicles for now. And so really excited that that will allow a lot more operational flexibility for EV fleets to move freight around the area.
31:45 Speaker 03 And so we call it a lane in the freight industry. So the lane between the port and the inland empire is a very important lane. And having charging on both ends just allows a lot more confidence electrification. Having the capability to maybe have a contract that allows access to both sides, which we're seeing the demand for now, is also really freeing and exciting for customers. If they had to do that on their own, they would have to figure out a location that they had to find access to near the port and one near the inland empire. And oftentimes, these are drayage companies where their main operations may be near the port, but they are just delivering to their customers in the inland empire. And so don't really have access to sites there. So super exciting that this will be the first node in the network.
32:30 Speaker 03 You mentioned the I-10 project, and that's also super exciting. And this is also the first node in that. What's interesting is, you know, we know that the site's corridor will take a little bit of time to build. And already, as I mentioned at the top of our discussion, that technology is starting to change. So those sites are generally about 150 miles apart. We know that the range is generally much, much longer than that. Another thing that's happening is we're starting to see standardization of the charging infrastructure. Seems really simple, but the connector has to be the same from all the charging providers and all of the trucks have to use the same connector. And so there's a global body called Charin that has been working on that protocol for quite a while now. It does seem like that they're finally at a place where that specification is built
33:14 Speaker 03 out enough that we have confidence of what to build along that corridor that could serve any kind of truck. You know, our customers are not generally going to have just one type of vehicle. They will have multiple models in their fleets. And so they want to know that if they have a contract with us or anybody else, or even if they're putting in, you know, infrastructure behind their fence, that they don't have to put in different infrastructure for different vehicles. That just sounds crazy to a fleet, right? But we are starting to get that maturity in technology in the industry that's really making that project super exciting and viable.
33:44 Speaker 02 If I wired $100 million into Terawatts Bank account tomorrow, what would you do with it?
33:49 Speaker 03 You know, I mentioned the location piece and I think that we're already doing this and so maybe it's not, you know, different. And we have raised quite a bit of capital, so we have a little bit of freedom to do this. But, you know, I would make sure that we're investing into the next generation locations where we know this will be needed. So sometimes, you know, there's places where there just is no power. It will take four to plus years to get there. So if you're able to have that site and start to develop it quicker, you would have that when that demand comes to that market. But I think the thing that we are really thoughtful about right now, and I think that we're going to be able to do a lot of great work with, is how we use the energy that's available at a site. So there's a lot that we're learning, again, from seeing the utility of these sites.
34:33 Speaker 03 And, you know, these sites are designed for every vehicle to come in at the exact same time and be the top of the charge curve, pulling the full power of the charger at the same time. And that just doesn't happen. And so there are ways that we can actually, you know, we have seven megawatts in the street, you know, of power from the utility at our heavy duty site, but maybe instead of serving, you know, 20 chargers, we can serve 25 chargers with that. So really. Or we can serve higher power at each charger with that. So I would invest it into making sure that we're being really thoughtful about that piece of it. Because again, I mentioned that power is the first thing that we always look for once we find those two other things. And being able to be more efficient with that is great for us.
35:15 Speaker 03 We have more capability at the site, but it's also great for the utility. You know, we're in an era where they are under pressure to do all kinds of things and, you know, build really fast for lots of increasing electricity demand. And so removing some of that pressure for them allows us to work more collaboratively with them as well. So I would invest it into that. I don't think it takes $100 million, but sometimes money is speed.
35:37 Speaker 02 But I love that a piece of your answer is making your financial team happy by making sure that you're optimizing and increasing utilization. So that's awesome.
35:44 Speaker 03 I always have to keep them happy.
35:46 Speaker 02 Thank you so much. This has been such an awesome interview. It's really interesting to hear about all the things that you've done on your journey and the challenges you've overcome. So we wish you all the best.
35:57 Speaker 02 Neha Palmer is a co-founder and the CEO of Terawatt Infrastructure. The Green Blueprint is produced by Latitude Media in partnership with Trellis Climate. The show is hosted by me, Laura Pierpoint. Our producer is Erin Hardick. Anne Bailey is our senior editor. Sean Marquand is our technical director. Stephen Lacey is our executive editor. If you'd like to suggest topics or guests for the show, send an email to [email protected] . You can listen to The Green Blueprint at latitudemedia.com or subscribe wherever you get your podcasts. And if you have fellow clean energy or climate tech travelers who would benefit from the insights in this show, send them a link.
36:40 Speaker 02 This is The Green Blueprint, a show about the architects of the clean energy economy.